Published Date:15/01/25
| Client: | Lendlease Construction (EMEA) Limited |
| Contractor: | Lendlease Construction (EMEA) Limited |
| Architect: | Eurban Limited, Hawkins Brown Limited |
| Location: | Deptford, London |
| Balconies: | 217 balcony lifts |
“It’s gone well on the whole – the experience with Sapphire has been very good.”
Envelope Package Manager, Lendlease
Once a royal dockyard, constructed under the purview of Henry VIII, the Deptford Landings project is a mixed-use urban regeneration development located in the northern region of the London Borough of Lewisham. Deptford is an area that thrives on its culture, with a community of creatively-minded people bringing new life to the area. Sapphire are thrilled to have been a key part in bringing Lendlease’s new Deptford Landings project to life, beginning with Plot 4, Deptford Wharves.
Lendlease began the Deptford Landings development with an ambition to use a CLT frame across the masterplan. CLT-framed buildings can often be more sustainable than traditionally concrete-framed buildings, is generally lighter-weight and can be prefabricated off-site, reducing construction time on-site.
We were aware from an early stage that this plot of Deptford Landings had a small site footprint to work with and very limited on-site storage available. This meant that not only could the balconies not be stored on-site awaiting installation, but it meant that transport logistics needed to be considered at an early stage.
Sapphire was able to ensure this project was streamlined by innovation using a combination of our brand-new Next Generation Cassette® system, Remote Locker Device (RLD) connection solution and our G60 anchor. Each of these elements allowed for a reduction in carbon footprint compared to our previous system and increased safety for installers on the project.
The innovative RLD connection meant that balconies could be pre-slung on the lorries and lifted straight into position as the connection arms were situated inside the balcony Cassette®. Furthermore, this meant that the initial fears of restriction on-site could be alleviated. Finally, using the G60 non-combustible anchor meant any concerns about fire safety within the CLT structure of the building could be remedied as the façade was now fully thermally broken and non-combustible in line with current building regulations.